Jared's RV-14A Build
Home
(1389 Total Hrs)
Avionics
(105 Hrs)
Firewall fwd
(39.5 Hrs)
Flying
(0 Hrs)
Op 38
(8.5 Hrs)
Other
(32 Hrs)
Section 10
(51.5 Hrs)
Section 11
(6.5 Hrs)
Section 12
(23.5 Hrs)
Section 13
(14 Hrs)
Section 14
(22 Hrs)
Section 15
(18 Hrs)
Section 16
(18.5 Hrs)
Section 17
(31 Hrs)
Section 18
(54 Hrs)
Section 19
(19 Hrs)
Section 20
(32.5 Hrs)
Section 21
(29 Hrs)
Section 22
(24 Hrs)
Section 23
(25 Hrs)
Section 24
(11 Hrs)
Section 25
(15 Hrs)
Section 26
(31 Hrs)
Section 27
(15 Hrs)
Section 28
(16.5 Hrs)
Section 29
(60 Hrs)
Section 30
(21 Hrs)
Section 31
(10 Hrs)
Section 32
(20.5 Hrs)
Section 33
(12 Hrs)
Section 34
(6 Hrs)
Section 35
(30.5 Hrs)
Section 36
(11.5 Hrs)
Section 37
(11 Hrs)
Section 38
(80 Hrs)
Section 39
(7.5 Hrs)
Section 40
(32.5 Hrs)
Section 41
(8.5 Hrs)
Section 42
(11.5 Hrs)
Section 45
(24.5 Hrs)
Section 46a
(32 Hrs)
Section 47
(29 Hrs)
Section 48
(20 Hrs)
Section 49
(19.5 Hrs)
Section 53
(6.5 Hrs)
Section 55
(47.5 Hrs)
Section 56
(4 Hrs)
Section 6
(13.5 Hrs)
Section 7
(26.5 Hrs)
Section 8
(32 Hrs)
Section 9
(47.5 Hrs)
Shop
(9 Hrs)
Vinyl wrap
(28.5 Hrs)
Wrap up
(89 Hrs)
More work on upper fwd fuselage
16 Mar 2017
5 hours
Section 35
#Upper Fwd Fuselage
#Fuselage
Share
Installed nutplates onto the center wire channel
Riveted the wire channel into the fuselage
Installed the canopy decks onto the longerons. Van's has you seal underneath them with tank sealant
Installed instrument panel supports to the canopy deck
I discover I was missing two brass inserts for the brake lines the other night when I was installing the brakes. They arrived this afternoon from Van's. So I took a few minutes and finished the brake line install
Counter sunk the holes in the instrument panel frame
Painted the instrument panel frame, then riveted on the nutplates